Renovation Grand Hotel Krasnapolsky Amsterdam

The hotel remained operational during construction

The entire hotel with all 282 rooms, public spaces and conference rooms is completely restyled

The project will occur in phases and will take about two years. The first phase concerned the monumental part of the hotel facing Dam square. When the restyling is complete the hotel will include a full service restaurant and bar, a gym and a luxurious spa. The hotel remained operational during construction.

  • 282 rooms
  • 2 years project duration

Several renovation activities

  • Completely restyling all hotel rooms and public spaces
  • Completely replacing existing installations
  • Repairing the facade
  • Applying exterior window frames
  • Repairing several wings

The hotel is located in a busy part of Amsterdam, so the municipality of Amsterdam has required us to avoid all unnecessary disturbance. Therefore, the transport of building materials happened at night and was combined with taking demolition materials away.

More information?

Niels Doodeman

Managing Director Heddes Bouw & Ontwikkeling

Niels’ passion for building is reflected at Heddes Bouw & Ontwikkeling, where they face challenges together. After holding a variety of positions, he has been a member of the Board of Management since 2002. In 2011 Heddes Bouw & Ontwikkeling became part of Ballast Nedam, for which Niels has final responsibility as Managing Director.

→ Visit the website of Heddes
Return to