Additional request
What was going on? Ballast Nedam Specialist Groundworks was working as a subcontractor on the Afsluitdijk project. Initially, the work involved standard activities, mainly excavating wet cofferdams. Once that was completed, there was an additional request to lift concrete elements. “We ended up working on that for another nine months,” Michel recalls. “During that period, the client’s site manager asked me to put a series of planks from the quay back into the water in order to vibrate them loose. I immediately thought: we’re absolutely not allowed to do that.”
Saying ‘no’
Clearly a valid point
What also helped was that the request involved doing something that didn’t seem feasible anyway. “The planks in question were still connected to each other,” Michel explains. “In that situation, it’s actually impossible to vibrate them loose in the way that was requested.” This became apparent when the client asked another subcontractor to carry out the task. “They did have the necessary certification, but they also indicated that they couldn’t perform those specific activities. So I clearly had a point.” The matter did not lead to any further issues. The client later showed understanding for Michel’s course of action. “I never once had the feeling that they held it against me.”