Contributing to the growth of the Port of Rotterdam

Four kilometres of civil engineering constructions

A24 Blankenburgverbinding

A new connection with an impact on the entire Rotterdam region. Commissioned by Rijkswaterstaat, Ballast Nedam, together with consortium partners DEME and Macquarie Capital, constructed the new A24 Blankenburg connection. The contract included the design, construction, 20 years of maintenance, and the entire financing of approximately €1 billion. With two junctions, a land tunnel, and a tunnel under the Scheur river, among other things, we improved the accessibility of the Rotterdam region and contributed to economic growth.


The A24 has been fully operational since its official opening on December 7, 2024. The link improves traffic flow and relieves pressure on surrounding roads. Ballast Nedam remains involved in the maintenance of the infrastructure through the BAAK consortium.

  • 4 kilometre sequence of technical constructions
  • 945 metres long immersed tunnel
  • 20 years maintenance

The A24 Blankenburgverbinding at a glance

The newly constructed A24 is a four-kilometer-long series of technical structures. We start at the A20 in Vlaardingen, where a sunken junction has been constructed. This sunken section runs southward and ends in a land tunnel. We then pass two viaducts and a flood barrier before arriving at the technical highlight: a sunken tunnel under the Scheur river that connects to an above-ground junction with the A15 in Rozenburg. In other words, it is a unique project that brings together all disciplines of infrastructure engineering.

Vlaardingen junction and Rozenburg junction

For the Blankenburg connection, we sought depth and height. On the north side of the project, you will find the Vlaardingen junction: the connection between the new A24 and the existing A20. This sunken junction is located approximately four meters below ground level, which has preserved the open character of the green landscape as much as possible. On the south side, the Rozenburg junction was built high up. With several flyovers rising up to eighteen meters above ground level, this junction connects the A24 to the A15.

A land tunnel with reinforced underwater concrete

The Holland Tunnel is a jack of all trades: it blends in completely with its surroundings and provides knowledge for other parts of the project. Reinforced underwater concrete was used to meet environmental requirements. This special construction technique led to less material being used and a reduction in CO₂ emissions. The tunnel was constructed at a lower level and the original grassland was restored on the roof. This technical structure was the first to be completed, which provided an opportunity to conduct tests and utilize the experience gained in the construction of the Maasdelta Tunnel.

 

Immersed tunnel operations in the heart of the world's busiest shipping channel

The biggest challenge within the project was sinking two tunnel elements that together form the Maasdelta Tunnel. To this end, the access roads to the tunnel were built on the north and south banks. Two tunnel elements measuring 200 meters long, 42 meters wide, and 8 meters high were constructed in a dry dock near Rozenburg. After being floated and transported, the elements were sunk to a depth of 27 meters. The access roads were then connected to the tunnel elements and the tunnel was completed. The result: a 945-meter tunnel that has been carrying traffic between Rozenburg and Vlaardingen since December 2024.

A long-standing relationship with stakeholders

Good environmental management is the basis for a project of this size. Together with Rijkswaterstaat, we invested in clear communication with local residents, government agencies, social organizations, and the business community. We held substantive discussions, remained in dialogue with each other, and communicated about the work in a timely and transparent manner. One of the tools we use for this is BIM. This allows us to provide all parties with insight into how the project is progressing and what it will ultimately look like.

Regular maintenance

Regular maintenance started in 2025. Throughout the year, there are nightly closures for inspections, cleaning of tunnels and installations, green space management, and minor asphalt repairs. Road users are informed in a timely manner via digital signs and detour routes. Ballast Nedam carries out the maintenance via BAAK. This maintenance contributes to a safe and reliable infrastructure.

More information?

Sander Lefevre

Managing Director Ballast Nedam Infra Projects a.i.

Return to